How Long Does a Conservatory Roof Replacement Take?

Two brick houses with tiled roofs and white uPVC windows against a clear blue sky

The short answer

A glass or polycarbonate roof swap is often finished in a day or two on site.

A tiled warm roof usually takes several days, because a new structure, insulation and a plastered ceiling all have to go in.

The paperwork can take longer than the building: with full plans, Peterborough has up to five weeks to rule on the drawings, or longer if you give it more time.

Ask how long a new conservatory roof takes and you will usually hear a number of days. That is the time the fitters are on site, and it is the part most people picture. But the clock starts earlier than that, with a survey, a quote and sometimes an application to the council. For a tiled roof in Peterborough, the paperwork can easily take longer than the building.

Time on site, by roof type

The type of roof is the biggest single factor. Here is a rough guide in general terms; your own firm will give you a proper estimate once they have seen the conservatory.

Roof type Typical time on site Why
Polycarbonate sheets Often a day or two Sheets go into the existing bars
Glass units Often a day or two Units go into the existing frame, which may need new bars
Tiled warm roof Several days New structure, insulation, tiles, guttering and a ceiling

These are not promises. Size, shape, weather and what turns up once the old roof is off can all add time.

What happens day by day on a tiled roof

A solid roof follows a fairly settled order. The first day is usually spent taking the old roof off and checking the frame. The next stage is building the new roof structure on top of the walls, and then come insulation, a breathable membrane, battens and tiles. Once the roof is weathertight, plasterers finish the ceiling inside and an electrician can fit lights.

If anything slows the job, it is normally the frame. When a fitter finds the side frames or base need strengthening, that has to happen before the new roof can go up.

The time before anyone arrives

This is the part that catches people out. For a glass or polycarbonate swap there is often no application at all, so once you have a quote you agree, the only wait is the firm’s diary.

Tiles change that, since a solid roof usually brings the Building Regulations into play. The two ways of getting approval run at different speeds:

  • Full plans: building control sees the drawings before anything happens. The Planning Portal gives the council a five-week deadline, extendable to two months only if you consent.
  • Building notice: skip the drawings, give 48 hours’ notice, then start, with an inspector checking on site as things progress.

A building notice is faster to start but puts more risk on you if something has to be changed. Full plans is slower but gives you an approval before anyone lifts a tile.

The Peterborough twist: conservation areas

Planning permission rarely comes into a replacement roof. As the Planning Portal puts it, most roof alterations are permitted development; only a roof whose look or build changes in a major way could need an application.

Peterborough has 29 conservation areas, including Park, Queens Road and Werrington in the city and villages such as Barnack and Wansford. If your house is in one, build in time to talk to the planners before you commit to a solid roof. It may come to nothing, but it is better to know early.

Following one Werrington job

Let us follow a made-up but typical job: a medium conservatory in Werrington, going from polycarbonate to a tiled warm roof.

  1. The homeowner gets a survey and a quote, then checks with the council because the house is close to the Werrington conservation area.
  2. The roof firm submits a full plans application to Peterborough City Council Building Control. The charge for alterations costing £10,000 to £20,000 is £564 with VAT on its fee page.
  3. Approval comes back within the council’s decision period, and the firm books the job.
  4. Fitting takes several days on site, followed by a final inspection and the completion certificate.

In this example the days on site are the shortest part of the whole process. That is common, and it is why it pays to start the conversation well before you want to use the room.

Ways to keep it moving

You cannot control the weather, but you can avoid the usual delays. Agree in writing who is making the building control application, clear the conservatory before the fitters arrive, and ask the firm to look hard at the frame at survey stage so there are no surprises on day one.

For guide prices for each roof type, see the cost page. For the rules in more detail, read building regulations in Peterborough. And to start with a firm that knows the area, go to the conservatory roof replacement peterborough homepage.

Prices for your own roof, from a Peterborough firm

Your postcode tells us which part of Peterborough or the villages you are in. The other three boxes are so the firm can ring or email you once you say yes.

You tell us where the conservatory is, we find one roof firm that covers that area, and we give you their name before a single detail of yours reaches them. You pay us nothing for this. How your request is handled

Where and who
Get a quote